Planning is hard, can we do Kanban instead?

Planning is an activity that usually results in some emotional response, however it can generally be said that teams avoiding planning will also be avoiding thinking about the future in general. A lack of robust planning the detail in your organisation can bubble up to impact plans at the high level portfolio, causing serious consequences on Lead Time and Delivery Rate.

Whether your experience with planning is a positive or a negative one, it is a skill that must be learnt and mastered.

When teams start out in Agile they will typically venture towards no planning or Scrum. Implementing Scrum first will generally be an easier task. A good litmus test for when you might be ready to try out more lean/advanced practices is when you feel the need to pivot more frequently than Scrum typically allows you to.

Ceremonious planning

Traditional software project management usually centers around some kind of ceremony when it comes to planning. This can result in situations where the granularity of planning can be too much, or the decision framework it provides is there to control change to a plan made in a previous planning session. This type of environment leads to progressively decreasing productivity. What the business wants to receive is prevented by the same framework that is supposed to aid it.

If a lot of your planning artefacts are going unused during development or need to be reworked entirely, then it is likely that you are over-planning.

Typically ceremonious planning leads to an environment where teams only communicate once per week (or month/quarter), and they are attempting to plan the entire week ahead.

No planning

An answer to ceremonious planning is to remove planning from the equation entirely! Meeting once a week? Who needs that?

This can work to reduce planning overhead massively, but this introduces the risk that business objectives wont be met. Highly performant teams will want to ensure they have appropriate robustness in their planning activities, and this is very rarely achieved by having no planning.

One solution is to go back to meeting weekly, right?

Scrum

Scrum answers this with a combination of sprint planning and daily standups, both of which have some amount of ceremony attached to them.

Sprint planning
The purpose of sprint planning is to put a timebox on a set of deliverables that the team has committed to, and offer that as an iteration cadence to the customer.

A sprint is usually planned every 1-3 weeks, and this can be a fairly heavy-weight session. It is hard for a Scrum team to change course in the middle of a Sprint, which may feel helpful for teams new to Agile, but highly-performant teams want to be able to change direction on a daily basis!

Daily coordination
The purpose of the daily standup is to improve team communication while in flight and there are three basic questions that create a standup meeting:

  • What did you do yesterday?
  • What are your plans for today?
  • Do you have any impediments?

This certainly helps teams plan their day within the context of the already planned Sprint.

It is common for team members new to Agile to be unable to grasp the importance of the daily standup, and to add to the potential pain points it can be time consuming when facilitated badly. Inexperienced teams tend to focus on what they are going to say during their turn in the standup. As a result of this they forget to listen to each other which defeats the purpose of having them, and can contribute to the feeling that they are boring or time consuming. The general suggestion is to ensure that these meetings are to strictly take less than 15 minutes.

Scrum requires team members to attend standup at the same time every day, for geographically non-colocated teams, or teams in different time-zones this can be logistically very difficult. This makes Scrum potentially inappropriate for agile teams with these scaling factors.

Lean-coordination (Kanban)

What is Kanban?
At the very basic level applying Kanban is as simple as having a Kanban board (e.g. on Trello) to visualise the flow of cards (Kanbans) through a work system, where each piece of work exists as a single item on the board. As Kanbans progress they typically individually move through a series of states, represented as columns from left to right, until they are complete.

The prevelence of such tools has enabled teams to create Kanban-like flow systems, dubbed Protokanban.

What does mature Kanban look like?

1: Defined commitment points
It is quite common for Protokanban boards to comprise of To Do, In Progress and Done columns. This is a potential sign that there is no defined commitment points, especially if requesters have write access to the board itself.

Risks associated with not having defined commitment points:

  • Perception that your team isn’t performant
  • Perception that Jira/Trello is a black hole for their tasks.
  • Knock on effects could be that requesters stop requesting tasks (which can lead to high value items not being ever looked at) or,
  • Requesters lose fundamental faith in the ability of the Service Delivery Team (SD Team)

2: Work in progress limits
To prevent SD Teams committing to all the work, Kanban imposes strict WiP limits.

Work in progress includes work that has been committed to!

As soon as the SD Team has committed to a work item, the clock is ticking until that work item is considered Done.

This forces teams to meet often with the Service Request Manager (SRM), who is roughly equivalent to the Product Owner in Scrum, whenever they have run out of work items to complete.

3: Prioritisation
Kanban coordination generally relies on the SRM pre-prioritising (and pruning) Kanbans before any coordination meetings.

Typically the prioritisation approach used by the SRM is centered around urgency modeling. Kanbans with higher urgency make their way to the top of the priority.

The main purpose of coordination is to apply weighted-shortest-job-first (WSJF), and select the tasks which have the highest Urgency associated with them with the lowest Cost-to-complete.

  • Weight is provided by a model of Urgency (which gets mapped onto cost in $ per week)
  • Shortest-job is estimated by team members (potentially ranged estimate)

Highly efficient Kanban SD Teams tackle the shortest-to-deliver most costly-items-to-delay first.

4: Frequent coordination meetings
This changes the focus of a Kanban coordination from the standard Scrum three questions, to a discussion about the work.

In other terms – which task am I doing next?

As a result of work in progress limits, Kanban SD Team members will generally meet as-and-when with the SRM. This means the SRM is a role that needs to be highly available.

Due to the heavy work focus of the coordination meetings, Kanban provides less of a feeling of team comradery when compared to Scrum. Adoption of Kanban works best for teams that have already proved that they gel really well. This is partly the cause of another one of the downsides of the Kanban approach: it may fail to discover collaboration issues and/or dependencies.

As the focus is on delivery to an external stakeholder to the SD Team, Kanban can also hide expectations between SD Team members. Extra effort must be placed on ensuring that internal expectations are voiced.

Scaling

It is recommended in Scrum to generally not scale a single team beyond 9-12 members (with even 9 considered extreme by most), by comparison it is generally possible to scale a Kanban flow-system beyond that (with teams seen in the wild at 40-50 members).

So a Scrum-approach or Kanban-approach?

In our experience Scrum is best suited for environments where the product development team is defining both the problem and the solution, and it needs to interact with the rest of the organisation to collect feedback so that it can locate problems. By contrast we have found Kanban to be extremely fitting in both this scenario and for steady streams of work-items, like support requests, that come from an external requestor. The benefit of Kanban is that it can be used internally within a product development team to pivot quickly, as in a lean-startup model, in this situation Scrum would feel like change-control beaurocracy. One consideration with the Kanban approach is that it works best in highly-experienced Agile teams. The reason for this is that it is a more lightweight governance approach, team members less familiar with Agile will struggle to keep focus.

About the Author

Avatar for Craig Bass

Craig Bass

Principal Software Engineer at Made Tech

Craig is a Principal Technologist and has been at Made Tech for over 7 years. In that time he’s seen Made Tech grow from less than 10 people. He was involved in running some of the earliest iterations of our engineering academies and was a prominent member of the committee (trailblazer) which co-authored the DevOps Engineer Apprenticeship specification.